Saxon Reach, Milton Keynes

September 15, 2020
 

L&Q set out to ensure high standards of product and low rates of repair and were reassured by our development designs, produced using our unique Design Standards of Excellence (DSE), our unique design guides creating variation within the development from within a structured framework which can be efficiently delivered.

  • L&Q are committed to procurement based on whole-life costs and low-carbon factors, a deciding factor in their decision to choose timber frame as part of their drive to embrace MMC.
  • L&Q’s USP on providing larger open plan living space has meant that on open plan narrower detached, semi-detached and end units portal frames needed to be introduced.
  • L&Q Counties are a new formed development division of L&Q Group – they have had a steep learning curve as timber frame was a new form of build for them.
  • The timber frame system brings superior insulation and guaranteed product quality which is being rolled out across a number of L&Q developments in the Counties.
  • All homes come with a 10-year NHBC warranty and 2 years of L&Q Customer Care.
  • SIGMA II 140mm closed panel with factory fitted windows – the party wall cavities are fully filled with edge sealing to achieve a 0.0 uValue, W/(m2K)
  • The roofs are standard trusses, top hat trusses, as well as closed insulated roof cassettes.
  • Education and Training Modules – Stewart Milne Timber Systems have been educating the newly recruited individuals and rolling out our training modules to ensure the houses were designed in line with their USP, which is quality and space standards.

Case Study

Paintworks, Bristol

August 18, 2020
 

Key Facts

  • PROJECT: Crest Nicholson Paintworks Exemplar Project
  • LOCATION: The site is located adjacent to the existing Paintworks development, on the River Avon, in Bristol
  • CLIENT: Crest Nicholson
  • SIZE: Paintworks is a mixed-use development in Bristol with the scheme comprising of the re-development of a 2.47 hectare brownfield site, and the creation of 11 live / work units, 210 houses and apartments and 6,700sqm of commercial floor space. The Crest Nicholson Paintworks Exemplar Project with Stewart Milne Timber Systems consisted of 96 units, split into 8 terraces of houses and 4 Blocks of Flats, with the timber frame element being an order value of circa £1.2m
  • TIMING: 18 Months

Type and size of project

Based in the heart of Bristol’s Creative Quarter, the original paintworks site was built in 1850 and used as a Victorian paint and varnish factory. This tight inner city site required speed and quality of build to deliver the project on time and within budget.

The development was to include a mixture of high rise concrete frame structures, including residential apartments and commercial accommodations, and timber frame townhouses with a high specification of external and internal features. As the scheme focused on the use of cycle routes and pedestrian links, logistical access to the units had to be accounted for in the project. There was also a requirement for the project to meet CSH4 and BREEAM Very Good standards, with a key focus on energy efficiency and sustainability.

Crest Nicholson, one of the UK’s leading residential property developers, appointed Stewart Milne Timber Systems to provide technical and operational support to design, manufacture, supply and erect timber build systems for the project.

The exemplar project phase had a start date of late September 2015.


Description of project

To address the construction needs, sustainability objectives, and on-site challenges of the project, a timber frame solution was utilised that involved small panels and loose joists that could be pre-loaded into position and then manually erected. This addressed the challenge of only one crane being available on-site, by minimising the “hook time” on this single crane. If large panel, floor and wall cassettes were utilised, additional cranes would have been required, which this tight inner city site could not accommodate.

A key driver in the specification of timber as the central construction method, was to meet the objective of reducing energy consumption. The low carbon credentials provided by a timber fabric construction contributed towards achieving this objective, along with speed and efficiency and the ability to work within the constraints of the phased occupation of the site.

In addition to energy efficiencies, the use of off-site construction with Stewart Milne Timber Systems brought several benefits to this project. The access limitations of the site for material offload and distribution meant that a panelised timber solution minimised site deliveries. This enabled a just-in-time delivery of timber panels and cassettes to be loaded directly into the working area, rather than composite traditional materials being double handled.

The overall cost of the project in timber frame was also very competitive due to speed of build and control of work in progress. Utilising Stewart Milne Timber Systems solutions ultimately enabled the buildings to be constructed quickly and safely ahead of programme, without compromising on quality. The timber frame construction method also enabled greater cost certainty when benchmarked against masonry composite building materials.

This exemplar project by Stewart Milne Timber Systems was completed in late March 2017.

Case Study

Larkhill, Salisbury

August 11, 2020
 

The MOD awarded their relocation scheme at Salisbury Plain to regeneration experts Lovell, involving the construction of over 917 homes across three sites in 2 years, to a strict deadline. To achieve this, offsite timber frame was the solution. The construction of the 450 properties at the Larkhill site was divided equally between two timber specialists – Stewart Milne Timber Systems and Taylor Lane Timber Frame – an unusual approach. The companies set milestones with their speed of build. With a handover rate of 16 houses every 10 days, the fast-track homes project is an industry exemplar and actively promoted by both companies as the future of building.

The achievement reached on the Larkhill site has been phenomenal – 2 rival companies building on site at the same time, both in timber frame, both increasing the number of plots built on site from 10 to 16 to meeting extraordinary completion deadlines. This shows what can be achieved when a collaborative, transparent and organised approach is taken by both parties.

  • Collaboration – Rival companies successfully working together on site. Both teams worked with Lovell from concept and design to current onsite build.
  • Speed of build. Both companies delivered 5 units a week, accelerated to a combined 16 units being completed on site every ten days. This project delivered exceptional levels of design, detail and delivery evidenced by delivering up to 16 units per week over 34 weeks.
  • Specification of the product. Found best solution to achieve thermal performance via design for manufacture, reduced risk, deliverability, ease of construction on site.
  • Reduced impact on local community and on the environment. Speed of build meant reduced loads, reduced traffic, fewer people on site, lower community impact.
  • This £250 million contract is part of Lovell’s largest ever scheme.
  • Daily meetings held by SMTS, TL and Lovell ensured exceptional communication between all parties. Both specialists showed great mutual respect regarding their shared objective.
  • Lovell requested certain key components be sourced through single suppliers to ensure consistency of finish. Both specialists were happy to work on this basis.
  • On time on budget delivery of the project. Everyone stepped up to meet the deadlines.

Case Study

Barry Waterfront, South Glamorgan

August 4, 2020
 

Taylor Wimpey were looking for an affordable offsite solution to provide the required number of units within budget and programme utilising as much offsite production as possible.
• The decision was taken to use a pre-insulated timber frame external wall system using 100mm PIR insulation.
• The wall system was fitted in a controlled factory environment enabling a high level of quality and for the units to be insulated before the houses were watertight, speeding up 1st and 2nd fix on site and resulting in the houses being completed more quickly.
• One result of the speed of build was a realisation of capital at an earlier stage of the build than previously anticipated.
• Pre-fabricated floor cassettes were delivered from the factory and craned into position providing a higher degree of quality and a safer method of working.
• The fascia and soffits were also fitted by the erect team to enable the roofer to have the houses and apartments watertight immediately.

Latitude is a delightful collection of new 2, 3 & 4 bedroom homes at the heart of the regeneration of Barry Dockland, a vibrant new community close to the seaside, the countryside and excellent transport links by road, rail and air. The Quays will include a host of new local amenities for the area, including waterfront cafés and restaurants, shops including two large supermarkets, a purpose built community facility, a hotel, a brand new primary school, plus new parks and green, open spaces. There’s a 2 year Taylor Wimpey guarantee plus a 10 year NHBC guarantee with every new home.